Jed Smith Pipeline Replacement Project

A sign with a flashing light reads "Under Construction" with a striped yellow background.

Hidden Hills

Replacement of pipeline to improve reliable water delivery.

July 26, 2017

The LVMWD Board of Directors has passed final acceptance of this project – it is now complete.

June 14, 2017

All homes along Jed Smith Rd are now connected to the new service line.

See the June 9 update below for a map of the affected area.

June 9, 2017

View updated construction schedule

On Monday, June 12, select customers residing on Robert Guy Rd can expect to be out of water service for a maximum of four hours sometime between 8 a.m. and 5 p.m. 

View aerial of potential homes affected

On Tuesday, June 13, select customers residing on Jim Bridger Rd can expect to be out of water service for a maximum of four hours sometime between 8 a.m. and 5 p.m. 

View aerial of potential homes affected

On Thursday, June 22, select customers residing on Round Meadow Rd may experience intermittent water service between 8 a.m. and 5 p.m. 

View aerial of potential homes affected

May 4, 2017

The contractor has installed pipe to Robert Guy Road and is continuing to the north. Temporary shutdown notices may be expected in the next two weeks, workers will attempt to keep shutdown times to a minimum.

April 26, 2017

The contractor continues to install the new pipeline along Jed Smith Road, progressing north towards Lewis and Clark.  The contractor remains on schedule and will soon submit detailed shutdown plans.

April 20, 2017

Crews have installed new pipe from Round Meadow to Jim Bridger and are continuing to trench and install towards Lewis and Clark Road. They are base paving the trench behind their work area and will perform the final cap pave once the installation and all of the services/connections are complete. 

The project is currently currently on-track with the original schedule (see April 10, 2017 below).

Roadwork scene with construction vehicles, cones, a car passing by, and traffic signs on a suburban street lined with trees.
A trench on a road under a metal cover, with construction equipment and traffic cones nearby.

April 10, 2017

Read the project schedule

Schedule subject to change due to weather or other considerations.

March 30, 2017

This project will take approximately 90-days begins Wednesday, April 5, 2017, finishing by the end of June, 2017.