Hidden Hills - Jim Bridger Road Pipeline Replacement

Under construction sign with a warning light on top.

City of Hidden Hills Jim Bridger Road Pipeline Replacement

This project will improve service reliability.  LVMWD will replace a 200-foot section of pipeline on an access road that provides service to 24944, 24948 and 24954 Jim Bridger Road.

See PDF file (below) for project details.

Update - May 7

This project has been completed.  

Update- April 3, 2013

The replacement pipeline is undergoing pressure tests, followed by disinfection/chlorination.

It is expected the new line will be in service by Friday, April 12.

Customers should expect a brief interruption of service when their homes are being connected to the new service line.

It will be normal to expect a few brief air pockets to work their through home plumbing after the new line is connected.

These “burps” will be temporary until the air clears the home plumbing system 

Initial posting: March 18, 2013